Transmission Constraints and Interconnection Challenges for Data Centers

American Bar Association
By Karen M. Kemerait and Vanessa A. Pinto
Share on:

Recent unprecedented demand for electricity, driven in part by data centers, is sparking intense debate across the country. That debate has spilled over into the U.S. Department of Energy (DOE) and the Federal Energy Regulatory Commission (FERC).

Electric utilities, grid operators, regulators, and data centers themselves are scrambling to find solutions for issues facing data centers. Fueled by the explosion of cloud computing, artificial intelligence workloads, and the digitization of the economy, utilities across the nation, including those in markets administered by regional transmission organizations (RTOs) and independent system operators (ISOs), are trying to connect up to thousands of megawatts (MW) of new data center load to an electric grid that is struggling to keep up. The numbers are staggering. The DOE’s 2024 U.S. Data Center Energy Usage Report estimated that data centers consumed approximately 4.4% of total U.S. electricity in 2023 and projected that amount to rise to between 6.7% and 12% by 2028. The International Energy Agency’s April 2025 Energy and AI report noted that a typical data center uses as much electricity as 100,000 households and that the largest facilities under development could consume 20 times more.

Data centers are running into a problem that no amount of capital can easily solve—they cannot receive access to power from the electric grid quickly enough. Utilities are struggling to build new generation and transmission infrastructure quickly enough to power these energy-intensive data centers. Delays impact when data centers will receive power, which could impact whether they will get built at all. There are no easy answers for this problem and the stakes are high.

Delays in Building Generation and Transmission

To power data centers, utilities need to construct a substantial amount of new electric generation and transmission infrastructure. But before new electric generation can be built and data centers can be connected to the grid, the electric system operators must determine the extent to which the existing electric system is capable of accommodating the new load, and if not, what transmission system upgrades are needed to integrate the load safely and reliably. In many parts of the country, particularly in RTO and ISO markets, two types of interconnection studies must be performed: a generator interconnection study and a load interconnection study. The generator study analyzes whether new transmission is needed to deliver the power from the generator to the data center, while the load interconnection study determines whether there is sufficient generation and transmission capacity on the grid to serve the data center.

Even before the recent demand for electricity from data centers, generator interconnection queues in many markets were clogged. The study process for new generators can be slow, sometimes taking three to five years or more. FERC, which oversees the country’s wholesale electricity markets and the transmission grid that supports them, recognized the urgency of addressing the generator interconnection backlog. On July 28, 2023, FERC issued Order No. 2023, Improvements to Generator Interconnection Procedures and Agreements, an interconnection queue-reform rule aimed at clearing backlogs in the queue and accelerating the study process. 184 FERC ¶ 61,054 (July 28, 2023).

Despite FERC’s reform, interconnection delays continue to persist in many areas of the country. For example, the mid-Atlantic electric grid is operated by PJM Interconnection, L.L.C. (PJM). PJM’s generator interconnection queue had become so backlogged that PJM effectively closed its queue in 2022 and stopped studying new generator interconnection requests. PJM used that time to study backlogged projects and work on generator interconnection study process reforms. In July 2023, PJM implemented the reforms and then resumed studying new generation projects. In April 2026, PJM touted the interconnection improvements, stating that most new generation interconnection requests will now be able to be studied in one to two years.

Delays are starting to dictate where data centers will be built. Virginia, the largest data center market in the world, is located in PJM’s territory. Bloomberg reported in 2024 that Dominion Energy had warned that PJM may be unable to support new data center connections before the early 2030s without significant upgrades to the transmission system that delivers the power from the power plant to the data centers. That constraint has pushed some developers to explore alternative markets in the Southeast and Midwest that may be able to supply power to them more quickly. The result could be a geographic redistribution of data center investment, driven not by market fundamentals but by electric grid access.

Data Center Interconnection Reform

What is happening in PJM is instructive for the rest of the country. PJM has estimated that electricity demand in the region will increase by more than 30 gigawatts between 2024 and 2030, driven largely by data centers. In an April 2026 Inside Lines update, PJM stated that “[d]emand growth [from data centers] is outpacing the addition of new supply, risking reliability and making the timely interconnection of new resources critical to keeping the lights on for 67 million people in 13 states and the District of Columbia.” The severity of the situation was underscored by PJM’s December 2025 capacity auction for the 2027/2028 delivery year, which failed to procure generation resources sufficient to meet PJM’s reliability requirement, falling more than 6600 MW short of what was needed for the reserve margin. PJM attributed the shortfall to a “transition gap” in which permitting and construction timelines for new generation resources could not keep pace with projected load additions driven by data centers.

Data centers have raised the alarm that there is not enough generation or transmission infrastructure to power their facilities and that new infrastructure is not being built quickly enough. The federal government has been paying close attention to these concerns. In an October 23, 2025, letter to FERC, the U.S. Secretary of Energy stated: “To usher in a new era of American prosperity, we must ensure all Americans and domestic industries have access to affordable, reliable, and secure electricity. To do this, large loads, including AI data centers, served by public utilities must be able to connect to the transmission system in a timely, orderly, and non-discriminatory manner. This is an urgent issue that requires prompt attention.” U.S. Fed. Energy Regul. Comm’n, Ensuring the Timely and Orderly Interconnection of Large Loads, Advance Notice of Proposed Rulemaking, Dkt. No. RM26-4-000 (Oct. 23, 2025) (ANOPR), https://tinyurl.com/33hahkes; see also Letter from Chris Wright, Sec’y, U.S. Dep’t of Energy, to Fed. Energy Comm’n, Interconnection of Large Loads (Oct. 23, 2025) (Secretary’s Letter). Acting under Section 403 of the Department of Energy Organization Act, the Secretary of Energy directed FERC to consider an Advance Notice of Proposed Rulemaking (ANOPR) entitled Ensuring the Timely and Orderly Interconnection of Large Loads. The ANOPR directed FERC to consider reforms to ensure the timely, orderly, and equitable integration of significant electrical loads, particularly from data centers, into the nation’s transmission system. Although many states have disputed FERC’s authority over load interconnection, the ANOPR advances four legal justifications for FERC’s authority: (1) large load interconnections are a “critical component of open access transmission service” requiring minimum terms and conditions for nondiscriminatory service; (2) such interconnections directly affect FERC-jurisdictional wholesale electricity rates; (3) the proposal does not impinge on states’ authority over retail electricity sales or siting of generation facilities; and (4) any contrary view conflicts with the Federal Power Act’s core purposes.

On June 18, 2026, rather than proceed through the traditional notice-and-comment rulemaking, FERC issued orders to show cause under section 206 of the Federal Power Act to all six major RTOs and ISOs under its jurisdiction, directing them to justify or reform the rules that govern how data centers, manufacturing facilities, and other large energy users connect to the electric grid. The orders identified five categories of reform: (1) establishing clear and efficient application and study processes, including evaluation of grid-enhancing technologies; (2) preventing cost-shifting to other transmission customers; (3) accommodating co-location arrangements and behind-the-meter generation; (4) providing transmission service for flexible large loads; and (5) developing processes to study generating facilities serving co-located large loads. FERC emphasized that its show cause orders are not intended to disrupt existing agreements that large loads have negotiated for transmission service and that each RTO or ISO may define “large loads” for its own region. FERC also stated that its action does not intrude on state authority to select, site, and permit generating resources or to set retail electricity rates. FERC required the RTOs and ISOs to file responses by August 17, 2026, but all six RTOs and ISOs have requested 90-day extensions of time to respond.

Data Center Reform in Different Regions

Two regional proceedings (in PJM and in the Southwest Power Pool (SPP), the RTO that manages the electric grid across 14 states in the central United States) illustrate how FERC’s large-load interconnection policies are being litigated throughout the country. Most notably, proceedings involving PJM are being closely followed by the electric industry.

On December 18, 2025, FERC issued an order finding PJM’s tariff unjust and unreasonable due to its lack of clear, consistent rules for generators seeking to serve co-located loads, such as data centers, and for the transmission customers that would take transmission service on their behalf. FERC directed PJM to create transparent tariff rules; establish new transmission service options, including firm and non-firm contract demand service, designed to facilitate faster interconnection of co-located loads; and revise its behind-the-meter generation netting rules, which FERC found were no longer just and reasonable because of the shifting of costs and reliability risks. PJM submitted compliance filings to FERC in early 2026. FERC then issued a follow-up order that established just and reasonable rates, terms, and conditions for the new transmission services and directed PJM and its transmission owners to submit further compliance filings. The D.C. Circuit’s June 5, 2026, decision in PJM Transmission Owners v. FERC reinforced these principles, affirming that FERC may reject proposed tariff amendments that are not “just and reasonable” and reiterating FERC’s duty to ensure RTO independence from any “market participant or class of participants.” No. 25-1064, slip op. at 4–5 (D.C. Cir. June 5, 2026) (citing 18 C.F.R. § 35.34(j)(1)(ii)); see also Atl. City Elec. Co. v. FERC, 295 F.3d 1, 9 (D.C. Cir. 2002).

PJM launched “fast-track” mechanisms to accelerate generator interconnection, including its Reliability Resource Initiative (51 proposals totaling approximately 11.8 GW) and an Expedited Interconnection Track that FERC approved in June 2026. Thereafter on June 30, 2026, PJM stakeholders endorsed a two-part Reliability Backstop Procurement Plan, developed by the Data Center Coalition and a group of utilities including Dominion Energy, Exelon, Duke Energy, PPL Electric Utilities, and Buckeye Power. Under the plan, load-serving entities and data centers could ask PJM to procure capacity in a one-time auction capped at $555/MW-day, with the large loads that drive the need billed for the procurement cost. However, the stakeholders rejected all proposed “Connect and Manage” options that would have allowed PJM to curtail large loads during capacity shortfalls. PJM filed its proposal with FERC on July 31, 2026, in Docket No. ER26-3380-000 with the goal of commencing a Reliability Backstop Procurement on September 30, 2026. PJM’s proposal would chart a path to secure new generation resources against the 6,831-MW shortfall resulting from the recent capacity auction for the 2028/2029 Delivery Year. The Reliability Backstop Procurement would secure resources for terms of up to 15 years with a maximum willingness to pay equal to a MW-weighted average of $555/MW-day. PJM requested that FERC issue an order on its filing by September 29, 2026.

Related to its July 31, 2026, filing, PJM made another filing with FERC on August 13, 2026, in Docket No. ER26-3515-000 proposing an Interim Resource Adequacy Service (IRAS) (formerly known as “Connect and Manage”) for data centers and other large load customers that do not bring their own power supply to address system reliability. Pursuant to IRAS, when electricity supply on the grid approaches dangerously low levels, a new emergency procedure would notify utilities to reduce or transfer the electricity demand from new large-load customers ahead of any action that would serve to shut off traditional consumers, including residential consumers. PJM requested that FERC approve the tariff by October 12, 2026.

In another region, SPP obtained approval from FERC of innovative large-load frameworks. On January 14, 2026, in Docket No. ER26-1323-000, FERC accepted SPP’s High Impact Large Load (HILL) study process, establishing a 90-day study-and-approval process for interconnecting large loads. Subsequently, on June 5, 2026, FERC approved SPP’s “Conditional High Impact Large Load Service” (CHILLS) tariff, which allows SPP to provide non-firm transmission service to data centers and other large loads using available transmission capacity for up to seven years while those customers acquire firm service. FERC found CHILLS to be a reasonable approach to expeditiously interconnect and provide transmission service to new large loads while maintaining the reliable operation of SPP’s transmission system. Importantly, SPP retains the authority to curtail service when the transmission system is constrained or under emergency conditions.

Beyond the orders to show cause, FERC conducted a chair and Commissioner-led technical conference on PJM’s governance and stakeholder processes on July 23, 2026, to determine whether PJM’s existing governance mechanics impede the region’s ability to respond to data center–driven capacity and interconnection challenges. During the technical conference, the FERC chair pointed out that “PJM is facing a grave legitimacy crisis.” She also stated: “Some transmission owners are openly discussing leaving the RTO altogether. Put plainly, market participants have lost confidence in PJM’s decision-making abilities.” FERC threatened to impose reforms if PJM fails to adopt changes by September 2026.

Unanswered Policy Questions

For utilities, RTOs, and ISOs, FERC’s actions will determine how they balance the obligation to serve large new loads with maintaining reliability for new and existing customers. PJM’s recent capacity auction shortfall has highlighted the fact that supply is not keeping pace with demand. FERC has stepped in and is demanding action to solve the resource adequacy issues.

Another unanswered question raised by FERC’s large-load proceedings is jurisdictional. Where does FERC’s authority over transmission-level interconnection end and state authority over retail service begin? The ANOPR asserted that FERC’s authority extends to establishing minimum terms and conditions for transmission-level load interconnections but acknowledged that states retain authority over retail electricity sales, siting, and resource planning. The D.C. Circuit has consistently recognized that “FERC is a creature of statute” and possesses “only those authorities conferred upon it by Congress,” and that“[i]n the absence of statutory authorization for its act, an agency’s action is plainly contrary to law and cannot stand.” Atl. City Elec. Co. v. FERC, 295 F.3d at 8. The court also recognized limits on FERC’s Section 309 authority, holding that it may not “contravene any terms of the [Federal Power Act]” or “supersede specific statutory strictures.” TNA Merch. Projects, Inc. v. FERC, 857 F.3d 354, 359 (D.C. Cir. 2017). Some states have challenged FERC’s authority over transmission-level load interconnections altogether, arguing that connecting large loads is a matter of state retail service and resource planning. This jurisdictional dispute might continue to be litigated in the ongoing proceedings at FERC.

For their part, state commissions have not been idle. More than 75 large-load tariff proceedings were pending or had been adopted in 36 states as of early 2026, according to the Smart Electric Power Alliance, addressing retail rate design, minimum demand commitments, and exit fees. But the interaction between state tariffs and FERC’s transmission-level requirements remains uncertain, and state utility commissions will need to ensure that their retail-level tariffs do not conflict with federal requirements.

What to Watch for Next at FERC

The rapid growth of data center demand has placed FERC at the center of one of the most consequential infrastructure policy debates in recent history. FERC’s June 2026 orders to show cause to the six RTOs and ISOs, combined with its orders in the PJM and SPP proceedings, are creating the rules for how large loads will connect to the transmission system and how the electric system will remain reliable. FERC’s orders to show cause reflect the Commission’s decision to let regional solutions emerge rather than impose a one-size-fits-all rulemaking. But FERC also has signaled that it will step in and impose reforms if grid operators (specifically PJM) do not solve resource adequacy problems on their own. Continued attention should be paid to whether FERC will approve PJM’s proposed solutions—a Reliability Backstop Procurement and an Interim Resource Adequacy Service—and whether FERC will find that PJM has made sufficient governance changes to solve capacity and interconnection challenges. Attention also should be paid to state utility commissions’ decisions whether to require new large-load tariffs.


Reprinted with permission from the Fall 2026 issue of the Natural Resources & Environment magazine by the American Bar Association Section of Environment, Energy, and Resources Committee. All rights reserved.